Hi,

From a dynamic event in HR we are submitting report RPLICO10. This is transferring the chosen fields - as merge fields - to a Word document.

Now, we have moved this - as is - from 4.6c to ERP2004. Now all the date fields aren't transferred as date fields anymore, which causes them to loose their formatting. I cannot format them i Word either, since Word doen't recognise them as date fields.

Have anybody faced the same problem, and solved it?

Thanks,

Vibeke

2 REPLIES 2

aabhas_wilmar
Contributor
0 Kudos

Try changing the user specific settings. The Submit program logic would have build on external format. You would rather like to use CONVERSION_EXIT... FMs for these.

You may also like to change the settings in System-> User Profile-> Own Data

Regards

Aabhas

0 Kudos

The user settings are set as always. The date is formatted the way we want.

When I'm calling up Word from RPLICO10 in forground the dates are transferred corretly formatted. But submitting RPLICO10 from a z-program it now (in ERP2004) loses the formatting.

Regards,