Month Difference - Function Module needed

aasim_khan
Participant
0 Kudos
1,476

Hi Experts,

In my report, I am using mcs0-spmon as select options; one of my inputs where the user will enter month and year in the selection screen . e.g. 04.2008 to 07.2008

I want to calculate the month difference and it should not exceed 3 months. If it does, an error will be shown.

My question is -

Is there any Function Module by which I can proceed. How do I go about it?

Can anyone tell me a solution?

Thanks in advance

1 ACCEPTED SOLUTION

Former Member
0 Kudos
193

Hi,

concatenate '200804' '01' into dur_begda.

concatenate '200807' '01' into dur_endda.

call function 'HR_PT_GET_MONTHS'

exporting

first_date = dur_begda

second_date = dur_endda

modify_interval = space

importing

duration = duration-months

exceptions

invalid_seq_dates = 1.

Thanks,

Durai.V

Edited by: Durai V on Aug 12, 2008 6:33 AM

5 REPLIES 5

Former Member
0 Kudos
193

Hi,

Here is the piece of code....

what u can do is just supply the date from u which u want to subtract and value for subtraction u give 3 then u check the new date if it is equal to the date u have second its ok u can proceed else u give error message...

i hope u will get ur solution...

data: new_date type d.

CALL FUNCTION 'MONTH_PLUS_DETERMINE'

EXPORTING

months = - 3 " Negative to subtract from old date, positive to add

olddate = sy-datum

IMPORTING

NEWDATE = new_date.

write: / new_date.

0 Kudos
193

Hey I already know about this FM. I am using select-options. I know it's a bit weird, but after all it's a client requirement. He want From-To option in the selection-screen

Former Member
0 Kudos
194

Hi,

concatenate '200804' '01' into dur_begda.

concatenate '200807' '01' into dur_endda.

call function 'HR_PT_GET_MONTHS'

exporting

first_date = dur_begda

second_date = dur_endda

modify_interval = space

importing

duration = duration-months

exceptions

invalid_seq_dates = 1.

Thanks,

Durai.V

Edited by: Durai V on Aug 12, 2008 6:33 AM

0 Kudos
193

Hi Durai,

Thanks for your help. I really appreciate it!

Former Member
0 Kudos
193

Hi..

here is similar question...

regards

vivek