Hi Guys,

I was created the One project, subproject and Object in the LSMW.

How to transfer the LSMW, Development to Quality.

Could you ple suggest me.

Thanks,

Gourisankar.

4 REPLIES 4

Former Member
0 Kudos

Hi,

There are 2 ways for transporting LSMW data from a system to another.

1) Export/import

This method gives you the opportunity to select the subprojects or objects you want to transfer. Hence you don't transfer the object a colleague might have created and that should stay in development system.

LSMW -> Extras -> Export project

2 )Transport request

With this method, you can transport a LSMW project in full (you can not select the objects you want). With this method, the project will be transported as any other SAP object in a transport order.

LSMW -> Extras -> Create change request.

Regards

Kiran Sure

0 Kudos

Thanks.

former_member435013
Active Participant
0 Kudos

Hi,

Export:

- LSMW

- menu -> Extras -> Export Project

Import:

- LSMW

- menu -> Extras -> Import Project

Regards

Walter Habich

Former Member
0 Kudos

Hi

You can do ti in two ways ,

go to extras,

1 /.export project

2./generate change request