Hi Friends good morning.

in my program am calling 13 other programs with different selection screen, i want to execute this one after the other automatically. ie after completion of one program it should display next program selection screen automatically. please tell me how to do this .

Regards.

Prajwal.

Message was edited by:

prajwal k

1 ACCEPTED SOLUTION

Former Member
0 Kudos

HI,

do like this.

submit zex1 via selection-screen and return.

submit zex2 via selection-screen and return.

...................

if u do like this.the next program selection screen will be called when u say back in the selection screen of the program u r currently in.

suppose if u want to go to the next program selection screen from the program u r currently in u have to write the 2nd submit statement in the program u calling first and so on.

<b>reward if helpful</b>

rgds,

bharat.

10 REPLIES 10

Former Member
0 Kudos

HI,

do like this.

submit zex1 via selection-screen and return.

submit zex2 via selection-screen and return.

...................

if u do like this.the next program selection screen will be called when u say back in the selection screen of the program u r currently in.

suppose if u want to go to the next program selection screen from the program u r currently in u have to write the 2nd submit statement in the program u calling first and so on.

<b>reward if helpful</b>

rgds,

bharat.

0 Kudos

Hi Bharat.

thanks its working ,But screen change occurs only when i press back button,

is there any other way to overcome this problem

0 Kudos

Hi,

we will when we press back button only.if u want to get without back button u should write the 2nd submit in 1st program(zex1),3rd submit in 2nd program(zex2) and.....then it will go in a sequence.and while u come out of that program it come out in the reverse order(zex5->zex4->...zex1)

<b>reward if helpful</b>

rgds,

bharat.

0 Kudos

Hi..

I did what u told but its giving error . like ''maximum number of internal sessions reached when i execute the 6 program

i have 13 programs to call

Regards

Prajwal.

Message was edited by:

prajwal k

0 Kudos

Hi,

here the problem is u can use the nested submit statements for 6 times only.

u cannot call after words.that internal sessions will be restricted by the basis people.

if u come back from one program u can use submit one more time.suppose if u come back from zex6 to zex5 then u can call zex7 successfully.

<b>reward if helpful</b>

rgds,

bharat.

0 Kudos

HI

can basis people change that .

0 Kudos

HI,

i think they can,i am not sure with that.

but one more thing if u don't want to came back from zex2->zex1,zex3->zex2,...

u just remove AND RETURN.the in that case u can call any number of programs

<b>reward if helpful</b>

rgds,

bharat.

0 Kudos

Thanks a lot Bharat.

u solved my Problem

Regards.

Prajwala.k.Nairy

varma_narayana
Active Contributor
0 Kudos

Hi

Use the syntax: to call all those 5 REPORTS..

SUBMIT <REPORT> VIA SELECTION-SCREEN AND RETURN ..

Here AND RETURN ensure the control to returned to Calling report every time...

<b>reward if Helpful..</b>

Former Member
0 Kudos

use

submit via selection screen and return

regards

Giridhar