Change fields in IF_EX_ME_PROCESS_REQ_CUST~CHECK

Former Member
0 Kudos

Hi guys

I need to modify a few fields at the time of recording the purchase requisition. I am using the BADI ME_PROCESS_REQ_CUST the method IF_EX_ME_PROCESS_REQ_CUST ~ CHECK, but when I called the method set_data, fields do not change. Anyone know of a solution?

3 REPLIES 3

VenkatRamesh_V
Active Contributor
0 Kudos

Hi,

Use this PROCESS_HEADER, PROCESS_ITEM.

Regards,

Venkat

0 Kudos

But i want chenge fields only when check or post the purchase requisition

0 Kudos

You cannot change things in the CHECK or POST methods; only in the PROCESS_HEADER, PROCESS_ITEM methods as Venkat says.  The logic is that you go thru these methods first so that by the time you get to the CHECK/POST methods that the data is finalized.

- Jim