AFAB - PRPS Relation (Network Relations - Work Breakdown Structure)

Former Member
0 Kudos
122

Hi Experts.

How can i find the relation between these two tables : AFAB-PRPS, i need to know wich Work Breajdown Structure are direct retaled with the Network relations in PS. Andy Ideas?, tnxs for your hlp.

1 ACCEPTED SOLUTION

former_member191977
Contributor
0 Kudos
53

AD03OBJTV - Plan data handling WBS objects, type and version

This is the table through which objnr is linked from AFAB.

AFAB & PRPS objnr is the field through which they are linked.

does this help you ? or else we can discuss more.

award points if it helps.

2 REPLIES 2

former_member191977
Contributor
0 Kudos
54

AD03OBJTV - Plan data handling WBS objects, type and version

This is the table through which objnr is linked from AFAB.

AFAB & PRPS objnr is the field through which they are linked.

does this help you ? or else we can discuss more.

award points if it helps.

0 Kudos
53

Vinni :

I've found the field you suggested, but when i check the values of both fields in both tables, they're different. Any Suggestions?.