hi all,

in RAR, job scheduler is running, but jobs are staying in ready state.

someone have an idea for my issue ?

it that i've done :

applied the SAP note 999785 (despite that the job scheduler is in running state)

restart j2ee server.

configuration :

GRC AC 5.3 SP10

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Aurelien,

Please apply following SAP Note and restart the system.

Note 1176262 - Analysis Daemon Page is Blank/ BG Jobs stay in ready status.

Best Regards,

Sirish Gullapalli.

Former Member
0 Kudos

Hi,

This is a very common problem. Most of the time, you don't have 'Virsa_CC_Config' table configured in RAR database. By following the above SAP note, you should be able to resolve this issue.

Alpesh