Activities involved in changing RFC connection from R/3 QA to R/3 PRD

Former Member
0 Kudos

Hi,

My current GRC system points to R/3 QA and all the data that is there in GRC system is imported from R/3 QA. Complete testing of the system has been done. Now I want to point this GRC system to R/3 Production. Does someone has list of activities and the sequence in which they need to be performed so that I am able to clean up the current data in GRC system that pertains to R/3 QA and import the data from R/3 Production.

Thanks in advance.

SP

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Downloand and upload can work but you will need to delete the rules once they are downloaded, if you ask support or contact me directly I can advise on how to delete the existing ruleset

Former Member
0 Kudos

Hi Frank,

Thanks for your reply. Can I export rules from my current system and import to logical system and then delete the same from current physical system?

Thanks,

SP

koehntopp
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

1. Create a message asking SAP for a cleanup script (there is no built-in functionality to do that)

2. Create a new connector for PRD

3. (Optional, but recommended: Create a logical system and add PRD to it)

4. Upload rules (ideally to te logical system, otherwise to PRD)

5. Generate rules

6. Run Full Sync users/roles (profiles if used/needed)

7. Run Initial Full Analysis for PRD

8. Schedule daily or weekly incremental sync & analysis

Hope I didn't forget anything

Frank.