Dear experts,
I received a request from a French user.
She said that, based on some local laws, it should be always possible to extract data as of a certain date.
For example, let’s say we have a customer that was originally saved with a certai...
Thank you @gianluca_taccone for the super-prompt reply!Just to check if I understood correctly: assuming that we set the system to check the due date for commitment and we will continue not to load multiple years' budgets, we "will need to live with ...
Dear @gianluca_taccone,thanks for the document.I have a question: in our case we load only the next year budget (as it's approved yearly), but for some OPEX, like maintenance, we have multi-year contracts.So, let's say, in oct-2024 we got 2025's budg...
Dear experts,I know of the DART-FEC: maybe that's enough, but I have no knowledge of the French legal framework.Any suggestion would be much appreciated!