Saif in my opinion debugging standart MRP should be last solution way. İf there is no suitable solution absolutely yes you can.Could you check the planned order marked constant ? If you are using MRP Live you can try regenerative planning.
Hello Saif,Firstly, Could you check availability check in SD/GEN view. When the fields is empty , planned order wont be update.Secondly, you can check "The reason for rejecting a sales document"Finally you can check requirements type in procurement t...
Your finished day is non working day in factory calendar. You mentioned "When input finish date as non working day(Sun)(26/03) in the process order creation." if you want to determine this date, It's should be maintain at factory calendar or work cen...
Hi For the BOM Component quantity update you can use "CSAP_MAT_BOM_MAINTAIN" FM you have fill (MATERİAL, PLANT, BOM USAGE, VALİD FROM, FL_COMMIT AND WAIT 'X' , FL_COMPLATE and TABLES T_STPO - Item category, ıtem no , component, comp qty, comp unit a...