We have checked by changing the Lot size EX, Planning calendar, MRP type and MRP run parameters . Still system is generating multiple sch.lines.
For some of the agreements its not creating and For some of agreemen...
We have checked all the mrp views
As per my understanding -Exception message 10 is , system is showing an message to create the sch.lines on that rescheduling date because demands were existing on past date
But requirements were not matching w...
backend job got failed with error " error determining planning periods for calendar 005"
We have maintained factory calendar from 2010 to 2028
Planning calendar is valid from 2020 to 2027.
There are no requirements in our system after 2025.
...
We debugged and found the issueWhich we not selected the variant (plant) in job. So that system is checking all the materials Some of materials are having different factory calendar, which is not configured with planning calendar.Thank you for res...
Hello Dominik,Thanks for your response.Background job and error found in SM37.Job will run for whole plant . We are trying to debug the issue.RegardsShantkumar