Hi experts,
I budgeted the WBS element from cj30.
I released the budget from CJ32.
But it comes as 0 in the S_ALR_87013560 report, you can see the screenshot.
Hi experts,
ı have a problem for sap ps.
When ı entering a budget in cj30, I added screenshot. After than ı run S_ALR_87013558 report, but the entered values are not correct in cj30.
CJ30 : 1 EUR = 15,09 TRY (False data)
S_ALR_87013558 : 1 ...
Hi experts,
My project coding mask is : AXXX.X.X.X.X.X.X
I want to change : A000.0.0.0.0.0.0
but when ı want to make change mask, system not allow. How can ı do it?
ı dont want to alphanumeric char. in my mask
Hi experts,
I have a problem for sap ps budget system.
For example, ı am entering a 1000 usd budget and ı spend 1500 try. But ı am getting over budget error.
exchange rate : 1 usd = 18 try
Hi experts,
I want to see and select template wbs elements when creating the project. How can I create template wbs elements?
I don't want it from the CJ01 tcode.
Thanks for your answers.