Dear experts,
We have an issue that assembly processing with networks does not work when forwards scheduling is defined in "Specify parameters for network scheduling".
The following error appears:
Error when processing Network
Message No. V13...
Dear SAP experts,
When using delivery from project (CNS0), delivery type LP, the standard Movement type for GI is 281(Q).
For a customer this needs to be changed to 601(Q) for the COGS split.
Valuated project stock is in use.
Is there a way...
Dear all,
I have a hard time to find out the difference between WBS scheduling and Network scheduling in the project systems.
Could someone explain the differences to me?
Thanks for your help!
I can confirm that 281 is hard coded and can't be changed. We will apply the COGS split to Movement type 281 and create a new movement type for normal consumption
Hello Ken, Thanks for your reply. I believe you are right that delivery from project always picks 281. Will check if the COGS Split can be applied to this movement type. Will let you know the results.
Hello Gokul,Thanks for your answer. Unfortunately this will not solve the issue, the delivery is still picking up 281(Q). Also I believe when chaning OPT1 you are not changing this only for delivery from project but also for normal goods issue to net...