Is it possible (maybe via some config) to have the MRP Element indicator "End of Planning TIme Fence" show up in the Project Stock MRP segments rather than in the "Stock" segment when using grouping? We use PS (GPD).
MRP has found 16 messages in group 1 and 6 messages in group 2 (obviously of course). However, remember that you will not necessarily see all the message in MD04 as only the first one is shown on the screen. You need to "click" into the order to s...
This is a little complicated to answer without knowing more about your landscape. If you're in two separate "boxes" then it's one technique or if in the same landscape it's another. But basically there are a number of ways to do this (interfaces)...
There is not a standard report that will tell you how many times inventory dipped below SS level. You could probably "easily" create one though. You could key off MRP Message 96 (Stock fallen below safety stock level.
It's possible if you're talking about the email address in the Communication section for :Address. This is configuration (SPRO) but T-code is OMSX (Transaction-Dependent Field Selection (vendor). Then select Change/Create Vendor (Purchasing). Then...