I am trying to create cost estimate for project manufacturing scenario - where materials are not yet created during quotation stage. Hence idea is to make use of Base Planning Object (BPO). Per S4HANA simplification list, T-code CKUC (Multi level uni...
Dear PS Experts,In the project I have issued materials, the actual cost is updating correctly at activity level. If I check CJI3, there also it is getting updated. But the component line item shows plan cost, not the actual cost.How to get it?Thanks ...
Dear Experts,I am trying to work with Cost forecast work bench. As per the information in network activity:Plan Quantity: 695 hrsConfirmed Qty:69.5 hrsForecast value:( 695 - 69.5) = 625.5But in the work bench: Forecast Remaining Quantity appears as :...
Network w/o project created from sales order. Subsequently when Network is changed and saved or Sales order is opened for edition(Va02), ABAP run time error.comes: We are using a material of type Service(DIEN). Essentially a service order where in th...
Hi All,We are implementing PS,MM,SD,FI &CO for a companay which works essentially on engineer to order scenario and using vlauated projec stock & actvity account assigned networksInhouse production is through typical assembly processing process - Whe...