Hi, I have a query regarding procurement proposals (planned orders) creation. Currently my plant has requirements from various customers. Each customer has multiple ship-to parties with standard pack size(lot size). For example: 1200 - General M...
When i am trying to set the 'DLFL' and 'TECO' for the given production order, i am getting the below error. I want to set the deletion flag for the order to delete the reservations for this order.
Hi allCan anyone please elaborate the difference between Net Requirement Calculation and Availability Check? As far as i am aware net requirement calculation does create planned orders and purchase requisition if there is no stock.RegardsSandeep
Hello,Can anyone tell me how to calculate the receipts in MD04? Number of periods : 3Type of period length : 3Days per period : 30I know how to calculate daily requirements. But this receipts is confusing.Here is my PIR:Thank you
Hi all !!Recently i have been trying a lot to fix this problem but i was unable to solve it. Problem: I was doing Semi finished product of STRATEGY 70 with combination of Finished Product of STRATEGY 20. But i there is no consumption of PIR in semi f...