Hello All Experts,I am facing an issue, while assigning material for network activity, Cost Element is getting defaulted to 400000. See below image -  But when I checked the settings for Network Profile in OPUU, its all blank. No default cost element...
Hello All Experts,I have two instances where Work Center is visible and another place where Work Center is not visible in Network (Internal Activity). Pic 1 - Work Center visible.Pic 2 below where Work Center is NOT visible. How can I make Work Cente...
Hello All Gurus, Client wants to add new option here as new PR type as a custom option - say 3rd Radio Button as - ZENO Purch Requisition I have searched many threads here but didn't find anything much fruitful. Can someone please let me know how do ...
Hello All Experts, One question, currently for Network-Materials system is creating Reservation instead of PO. What settings/configuration I need to do or required, so that system will start creating PO and not Reservation. Business wants PO to be cr...