on 2024 Feb 06 3:54 PM
I have added a new attribute in a standard Data Model, but right now it is in the release state for production. However, a few of the opening CRs are in in-progress status (not FINAL CHECK APPROVED) in the production pipeline.
Just need to know whether my production release of the newly implemented attribute will or will not affect opening CRs. If it does, then what procedure must be followed?
Thanks in Advance!
Request clarification before answering.
Hello @JayeshHati1997,
The open Change Requests must be re-aligned with the "new" version of your data model. To do so, please execute the report USMD_ADJUST_STAGING.
Best,
R.