TECO status

Patil1
Explorer
0 Likes
658

Hello Experts,

 

1. Please tell me the sequence of settlement scenarios for the capital project.

2. After TECO status, is a good issue possible or not?

I checked the system status (BS23). Good movement is allowed, but when i create good issue against reservation I face some issues.

Please Find attached Screenshots.

SYSTEM STATUS.PNGAfter TECO Status Good Issue.PNG

Accepted Solutions (0)

Answers (2)

Answers (2)

MarcioBlos
Active Participant
0 Likes

Hi Patil.

When you apply TECO system status the reservation created from the material component is closed, meaning the requirement no longer exists. However, you can still manually post goods issue. You can also reverse the TECO status so that the requirement will be 'reopened,' and the reservation can be used again.

Regards
Marcio Blos

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Likes

Display the reservation to see if it is still open.

Patil1
Explorer
0 Likes
Reservation closed.
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Likes
Then you can't post a GI to it. You can either reverse TECO or just manually post the GI.