Hello All,
We have implemented standard change in our CHARM and solman version is 7.2 sp 9.
At the being implemented state of request for change standard change is getting created, Now we want a configuration that will mark parent request for change to confirmed state when a standard change is moved to imported into production state. Our standard change transaction type is ZMSG and RFC transaction type is YZCR.
Regards,
Saikat
Request clarification before answering.
Hello Saikat,
In sm34: aic_settings2 you can see that this is already delivered for the standard transaction types
I guess this is what you are looking for.
Best regards,
Dolores
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 5 | |
| 5 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.