One of our processes is generating about a 1000 IDocs through RSEOUT and calling CPI to send the information to a 3PL application. What we are seeing is about 600 of those IDocs reach CPI and get processed successfully and the remaining 400 IDocs end up in Status 02 status indicating it couldn't connect to CPI. We don't even see them in CPI. 

Does anyone know if there is a max CONCURRENT connecting limit in a CPI tenant and how to have it updated?

Thanks in Advance

Accepted Solutions (0)

Answers (2)

Answers (2)

MAVR
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi @ADIDAS 

Please get in touch with the operation team (open an SAP case LOD-HCI-PI-OPS) and provide the detailed volume you are having and your tenant information. They will validate and increase the resources accordingly. 

I had a similar issue with SOAP services S/4HANA, which was unable to reach BTP Cloud Integration, but after the changes, the issue was solved.

I hope this helps you. 
Best regards 🖖🏻

 

ONavas
Participant
0 Kudos

Hi ADIDAS,

For outbound processes with many IDOCs, the best practice is to activate the option Collect IDocs and to use a Pack Size according to your requirement.

For 1000 IDOCs, 50 or 100 value for Pack Size should be a good option.