Hello Everyone,

Our customer plans to upgrade to S4hana using greenfield implementation. How ever they plan to use the existing BW system on Hana DB for their greenfield project. I have following questions regarding that:

1.) Being a BW consultant what activities I need to perform if I want to use the existing standard contents which are already activated.

2) If customer plans to use existing reports (standard & customized) in greenfield implementation , what setting or configurations do I need to keep or change? for eg: if for LO extraction/inventory management, customer plans to reuse the existing reports , infoproviders ,DTP etc and just change the connection and import data from new S4hana system, what activities should I perform?

If the BW system had been a new system, then I would have build everything from scratch. But using the existng BW system with a new S4 hana system is making me confused.

Kindly give me an insight or roadmap in these regards.

Accepted Solutions (0)

Answers (0)