a month ago
sac using dataaction copied data from actual Q1-25 to Q1-Budget.In budget manually unable to edit data for Q2. Note data avaliable in actual for Jan,Feb,Mar,April-25
Roles i have : Application Creator;BI Admin;BI Content Creator;BI Content Viewer;Modeler;Planner Reporter;Predictive Admin;Predictive Content Creator;Viewer
License: Planning Professional
Iam facing below error
Request clarification before answering.
Hi @yoursraghu986,
Check below setting either planning is enabled or not on table
If this is a calculated account or measure, you won't be able to edit it.
For edit calculated account you need to write Inverse.
Kindly upvote!
Thanks