on 2023 Sep 15 10:22 AM
There is a need to transfer safety stocks from IBP to ERP ECC using CPI DS.
Is there some kind of standard template or guide?
Kind regards,
Serhii.
Request clarification before answering.
Hello,
You can use any key figure extraction template and replace the Source Key figure in IBP with the 'Safety Stock' key figure and publish it to ECC.
You can create your own as well. In the target system ECC, you just have to update Standard table (MARC) or custom table based on your business process configuration.
Thanks
Gaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Here are the list of IBP templates explained in details:
https://help.sap.com/docs/SAP_INTEGRATED_BUSINESS_PLANNING/eab8fd1726934516a89eabced318b210/c14c1155...
Regards,
Bence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
In addition to the Gourav's comments above I only wanted to highlight that the main gap is that Safety stock in IBP is time-series data and in ECC safety stock is static value.
So you need to decide what you want to do.
- aggregate and make safety stock results in IBP as static and then send it to ECC as static value
- develop a custom table with "time" as a additional dimension in ECC, load dynamic safety stock results to this table and then put it to material master each time bucket. It is still not a really dynamic safety stock, but rather "pseudo-dynamic".
Regards
Lev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 7 | |
| 6 | |
| 6 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.