Hello All,
We have started replication for ACDOCA table using SLT. As ACDOCA has around 2.7 Billion records in source system we have used ranges (divided into 5 ranges based on one of the Key fields) to complete the calculation faster. No. of jobs defined in SLT configuration as below:-
No. of data transfer jobs. 22
No. of initial load jobs. 20
No. of calculation jobs. 10
Once we start the replications there 3 calculations triggered in source system. As each range has around 500 to 600 million records calculation jobs are taking time.
Is there any way we can run 5 calculation jobs in parallel in the source system?
Note:- We have enough resources (background, dialog work processes) available in the source & SLT systems.
Regards,
Vinay
Request clarification before answering.
Hi Vinay,
which version of DMIS used?
i also suggest to check from LTRS -.performance option - general performance options -No. of parallel jobs,
you can not increase parallel job once replication start for a table, if required that can be changed from LTRC - data transfer monitor - select table - click on change tab- increase the mx. parall. load pro. from access plan/pre-calculation setting but this will trigger again calculation job and initial load.
if required then change parallel job for specific MT ID will be effective for all tables once replication started for tables.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
66 | |
9 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.