We would like to control the number ranges for MRP created Purchase Requisitions on plant level.
How would it be possible?
Thank you!
Request clarification before answering.
It is possible to control the number range on plant level for MRP created Purchase Requisitions in SSCUI 102397 – 'Assign Number Ranges for MRP Run to Plant' to set the number range only on plant level, not for a specific Purchase Requisition document type.
See further details in this SAP KBA:
3485654 - Number Range control on plant level for MRP generated PR