on 2024 Jun 28 7:33 AM
Hi,
For Table split preparation in swpm, SAP guide states that
"Parallel data export of a table is supported by all database platforms but not parallel data import. When the target database platform does not support the parallel data import, the migration monitor has to be configured in the way that the data import processes the packages are sequentially."
Question is: Does HANA db support parallel data import from table splits ? e.g. Once the export is completed, then Can 6 splits of BSEG-1 to BSEG-6 or CDPOS-1 to 6 table be imported in parallel or out of sequence ? since multiple parallel import jobs would be available ? Will it cause any problem ?
Thanks / regards.