on 2025 Feb 13 3:32 PM
Hi experts,
we currently have a production process on a button in the operation activity POD. I have mapped the input parameters, also including the operation activity. If we execute the button with several operation activities marked, then only one operation activities is transferred to the production process. I would have expected that the process is done several times with all transferred operation activities or that they would have been transferred in an array as one input parameter.
Does anyone know if it is possible to transfer several operation activities to the production process?
Thank you!
Request clarification before answering.
Found it by myself: just define the input parameter in the production process as array 😁
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 6 | |
| 6 | |
| 5 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.