on 2024 Jul 11 9:55 AM
Hi All,
We have specific project configuration and test data available in TST Client 100 but not moved to PRD 100.
We are planning DB refresh PRD to TST so specific project configuration and test data will be delete in TST.
To avoid this situation, we are going to take Client export and after DB refresh activity completed in TST, we will create a new client 200 and will plan to import the data. TST have test client 100 and additional 200 client for specific testing.
FYI: we are using CHARM for all TR movements.
Now My question--> Can we import Client export Transport request number via STMS then we will perform post import process via SCC7 or SCC7N.
Is this will impact CHARM TR process(Manual client Export TR via STMS_IMPORT)???
Please advise.
Request clarification before answering.
| User | Count |
|---|---|
| 18 | |
| 7 | |
| 6 | |
| 6 | |
| 4 | |
| 4 | |
| 4 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.