on 2024 Aug 02 10:50 AM
Hello everyone,
I would like to adjust the batch of an existing production. This should not be done on component level but rather on the production order header.
I have already tried the following options:
CO_XT_COMPONENT_CHANGE
BAPI_PRODORD_CHANGENone of them worked.
Thanks in advance for any further ideas.
Kind regards,
Lukas
Request clarification before answering.
Hello @lukasmetzger
Changing production order batch is a missing functionality of BAPI_PRODORD_CHANGE.
It's delivered with the note 3492667 - Changing batch of order header item via BAPI. Get the note implemented and you'll be able to modify production order batch with the BAPI.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 7 | |
| 6 | |
| 6 | |
| 4 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.