Hi all,

I have created some Requirements and wanted to change it to a Project Task. I have tried to export from excel "for update" change the type to "Project Task" and reimport, but the the type is not changing and stay as "Requirement". Anyway to change via Mass or via excel or any other way, to not create them again one by one as a task?

Hope someone can help me...

Thank you in advance!

Kind regards,

Accepted Solutions (1)

Accepted Solutions (1)

robin_schoenwald
Product and Topic Expert
Product and Topic Expert
0 Kudos

It is not possible to change the type Requirements into  Project Task. But there is a workaround:

  1. Download Excel "For Creation Using Template"
  2. Change the type in the Excel file to “Project Task”
  3. Switch to the Tasks App and upload the Excel file
  4. If anything is ok, delete the requirement