BAPI_CONTRACT_CHANGE is not updating the Net Price in Outline Agreement for Future dates

poojithaK
Discoverer
0 Kudos
210

Hi Team,

we have a requirement to add the scales and condition amount in outline agreement. we are using BAPI_CONTRACT_CHANGE and it's working as expected but the net price in the outline agreement is not getting auto determined and this is happening only for future dates.

Example: today's date is - 6th May 2025 and I have created a new validity period for 7th May 2025 and added the scales and condition amount using BAPI_CONTRACT_CHANGE, so when my system date is changed to 7th May 2025 it has to change the net price in the outline agreement automatically but the Outline Agreement is having previous validity period's condition amount as net price which is not correct.

poojithaK_0-1746523071587.png

poojithaK_2-1746523109241.png

poojithaK_3-1746523149723.png

Note: we are triggering this BAPI from BTP system (UTC time zone), and SAP system is in PST time zone. mentioned this point to get my doubt cleared as I am thinking this might be a time zone issue.


Please suggest a solution. Thankyou!

 

View Entire Topic
RaymondGiuseppi
Active Contributor
0 Kudos

Please check if the note 3126346 - Netprice is not changed for an outline agreement item via BAPI is relevant for your system.

poojithaK
Discoverer
0 Kudos

HI Raymond,
This SAP Note is not relevant to our system.

RaymondGiuseppi
Active Contributor
0 Kudos
Then wait for tomorrow (actual PST)
RaymondGiuseppi
Active Contributor
0 Kudos
Was the net price displayed correctly the next day?
poojithaK
Discoverer
0 Kudos
HI Raymond, Net Price didn't update correctly the next day
RaymondGiuseppi
Active Contributor
0 Kudos

It seems that either the RM06ENP0 report still needs to be run, or the contract still needs to be manually modified using ME32K. 🤔