To move a transport from one client to the other please follow the below steps.
1. Go to SCC1 T-code
2. Provide the source client.
3. Provide the Transport number.
4. Select including request sub-tasks if the child Transports also need to be moved.
5. Select schedule as background job (if you are opting multiple transports to be moved) or you can run it immediately, if you are sure that the activity wont consume the WPs for a longer period. The status of background run can be checked in using SCC3 T-code.
6. Add the request to the import buffer using STMS_IMPORT
7. Import the request