2011 Jun 02 8:10 PM
Hi,
Can we have KPI targets with decimal values? Can we have KPI targets in descending order?
I use the Index value of the KPI to set the target and I'm not able to do it.
Thanks,
François
2011 Jun 09 5:00 PM
Francois,
Targets are set in a BEx workbook and you set the values for variables there. You save the targets in the workbook and it will be stored in the SuPM planning cube, which should make it available for reporting.
I recommend the SDN blog about setting targets:
http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/0088043c-51ea-2d10-449e-b4b9a9f28e3a
Regards,
Bob
Edited by: Bob McGlynn on Jun 9, 2011 9:09 AM
2011 Sep 23 12:04 PM
Hi,
In order to maintain the decimal values for the Target KPI, you should have the Keyfigure which supports the Decimal values.
To check this, go to the Planning Infocube and select the Key figure (Amount/ Quantity).
Double click on the Key figure and go to "Additional Properties" tab.
Here, you can find the Decimal places that are allowed for that KPI.
You can select according to your requirement.
Hope it Helps.
Regards,
Raghu