Hi,

We are receiving a set of ProductForecastNotification_IN XMLs from XI development system into our SNC development system.

These PFNs are having "Scheduled" status instead of "Processed Successfully" status.

Please help with you expert comments as to why the status is not changing? Also, what are the steps to process "Scheduled" XML messages.

Thanks & Regards,

Ujwal Arora

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Hi Ujwal,

There are few actions which you need to check:

1- Queue Activation: Go to sxmb_adm to register & activate queues:

Register & Activate:

2- Check interface dumps: Go to t-code slg1 and execute the report. You can see the dumps related to interface messages. These messages can help you to analyze the root cause.

3- Kindly control inbound queues from smq2 transaction. This t-code can show you also some clue related to your schedule.

If you still have the same issue then let me know the problem by adding slg1 & smq2 screen shots.

Regards,

Selim Batur

ujwalarora1982
Explorer
0 Likes

Hi Selim,

Thanks for the reply. It worked for me.

Thanks & Regards,

Ujwal Arora

Former Member
0 Likes

Hi Ujwal,

If you are happy with solution provided by me kindly take the actions mentioned in below post which is shared by Jürgen.

Regards,

Selim Batur