Can anyone please let me know what is the work center formula for Heat treatment work center?

Regards,

Jinto Joy

Accepted Solutions (0)

Answers (1)

Answers (1)

lingaiahvanam
SAP Champion
SAP Champion

Hi Jinto,

To create a new activity type follow the below steps.

Costing Parameters:

  • KA01 - Create Primary Cost Element for the new activities type.
  • KL01 - Create Activity Type tied to the primary cost element.
  • KP26 - Change Activity Type/Activity Price Planning - maintain the Variable price

Production configuration:

  • Create standard Value Key (transaction OP19) and Formula Key (transaction OP49)
  • Create Formula Parameters (transaction OP7B)
  • Assing the Standard value key in Basic Data and select the Formula Key in Costing tab with cost center assignment

Sample formula = (ZHEAT_09) / (SAP_08 X SAP_11)

ZHEAT formula = (Heat consumed X Production order qty) / (Base qty X Splits)

Please note this formula is an example you can adjust based on your requirmeent.