a month ago
hi All,
We are implementing PTW for SAP EAM Phase based methodology. Our client requirement is to assign one PTW for multiple Work orders, as they have daily inspection/ operation at heights or under water for which they do not want to raise PTW everyday for every single order.
Is there a process to create a PTW and keep it open for some days (14 days for example) and extend the same permit on need basis for multiple work orders, instead of creating a new permit for every single work order ? Also, can you please tell how does PTW/WCM work in case of emergency work orders?
PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM) #Permit to work
Request clarification before answering.
User | Count |
---|---|
5 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.