on ‎2016 Mar 24 6:58 AM
Hi EWM Gurus
I have tried to set up a POSC for a warehouse but till deconsolidation step, i was able to get the auto warehouse tasks but as soon as i complete the deconsolidation step(HU step Completed), i am not able to get the any warehouse task which should be created automatically. Can you please guide where to look into for resolving this issue ?
Thanks and Regards
Arjun Sai
Request clarification before answering.
Hi,
As per your storage process , after external process step PDCN, some external process step PQIS is mapped.
Can you check the POSC, either the destinations are properly maintained against the step PQIS.
if the system is not find the destination for next external step, even though you complete the external process step for HU, WT task can not be created.
BR
C K Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.