on 2022 Oct 16 1:27 PM
wpt.jpghello all,
in my case, i have created the task as soon as created the task it confirms immediately.
but in the unloading task or you can say in WPT 3065 i haven't maintain confirm immediately still whs task confirms immediately.
is any other configuration i need to check. please guide me
Hi Akash,
Maybe it is the following reason:
if your source Storage type has deactivated “Confirmation of Stock Removal Required” and your destination storage type has also deactivated “Confirmation of Putaway Required” than every Warehouse Task is confirmed immediately. Please check in Customizing:
Greetings,
Jan