on ‎2019 Sep 23 8:59 PM
Hi,
Following scenario:
- Inbound with Combination of Process Oriented Storage Control and Layout Oriented Storage Control
- Storage Types: Inbound Staging Area -> Intermediate Storage Type -> Destination Storage Type for Putaway
- Process starts with warehouse process type 1013
- Warehouse process type must be changed in Warehouse Task B (this is the issue)
Warehouse Task A:
WT to intermediate storage type (Inbound Staging Area -> Intermediate Storage Type)
Warehouse Process Type in LOSC would be relevant (if needed). For me no it is not needed, because warehouse process type 1013 is already in warehouse task.
Warehouse Task B:
- WT from intermediate storage type (Intermediate Storage Type -> Destination Storage Type for Putaway)
Which setting/customizing is needed to assign another Warehouse process type? In my case warehouse process type 1013 is also found. But I want use warehouse process type 1011.
best regards
Andi
Request clarification before answering.
Hi Andreas Wille,
What is the Warehouse Process Type in Inbound Delivery ? 1011 or 1013 ?
Are you using VAS for Inbound ?
SAP Standard Warehouse Process Type Description:
1011 - Putaway with Storage Process
1013 -Putaway with VAS Storage Process
Warehouse Process type in LOSC: Create WT to intermediate
Example: your case Inbound Staging Area -> Intermediate Storage Type
Kind Regards,
Ajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.