Valid Tlane is available between two plant but not appear or consider while creating the order in product view.
Getting below message in log
No transportation lane/procurement relationship for prod.xxxxxxxxx loc. yyyy
Message no. /SAPAPO/RRP013
Diagnosis
You have maintained external procurement as procurement type for product XXXXXXX in location YYYY.
System Response
The system could neither find a valid transportation lane nor an external procurement relationship
Why system does show or consider valid tlane ? Please advice
rgds
SDB
Request clarification before answering.
Solution - Mot was not maintained product wise otherwise "all product product' should be active in MOT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.