Dear Experts,

Good day!

I would like to ask for your help on how this Capacity Consumption key figure is being calculated in Capacity Leveling planning book/data view. As I understand, there's an assigned key figure function on this SAP standard key figure which calculates and computes for the values. However, as functional IT, I have limited familiarity on understanding the function via source codes.

Also, if possible, can you please help me understand the relation of this Capacity Consumption key figure and the variable, fixed duration master data at PPM? Appreciate your soonest feedback here.

Regards,

AA

View Entire Topic
alok_jaiswal
Contributor
0 Kudos

Hi,

Capacity Consumption key figure shows the total capacity of the production plant which is used i.e. for example a plant A has capacity of 700 units per bucket (i.e. day) and on a particular day based on requirements it created 350 planned orders. So, capacity consumption key - figure will show 300, Available capacity will be 700 and Resource capacity Level in % will be 350/700 i.e. 50%.

In below screen, you can see receipts per day are as shown 5000, 22800 etc. - these are the planned orders created at Plant -

Now if one looks at capacity planning view, you can see the capacity consumption key figure is populated with same values and % is what percentage of available capacity is used. Colors in red shows that capacity exceeds 100%

Hope it helps.

Regards,

Alok

former_member215376
Participant
0 Kudos

Thanks Alok.

As I understand, Distribution Receipts (Planned) will also be referred for the case of transportation resource. May I know the best usage of the transportation resource from the business perspective and why are some companies consider this as well? Can you site a specific scenario for this one? Thanks.

Regards,

AA

alok_jaiswal
Contributor
0 Kudos

Hi AA,

For details on transportation resources, please refer to below link -

Transportation Resource and Handling Resource for Stock Transfer - Capable-to-Promise (CTP) in PP/DS...

Hope it helps.

Regards,

Alok

former_member215376
Participant
0 Kudos

Thank you Alok.