Dear experts,

In our production system , the planned orders are not getting generated for the year 2021 in apo due to incorrect production cost setup in work center.

Please note this is only happening in the year 2021 for month of August.

Please suggest which area I have to look into as I am pp in the pp consultant with limited apo knowledge

View Entire Topic
Former Member
0 Kudos

Hi

Please check the Planning Parameter End date in General Tab of /SAPAPO/RES01 Resource Master for the Resource.

Thanks