on ‎2020 Jun 19 1:37 AM
Hello,
I have a scenario where a product can be procured from two vendors. I am using Transportation Cost Rate KF to set vendor priority (Product/Location/Ship To Location). No other cost setting has been set. The setting for Transportation Cost Rate in the first period is taken and used for the entire planning horizon. I am trying to time phase this where after a certain period, I want to switch the priority. Anything else that I may be missing? The only documentation I have found related using priority for source determination is link.
If any of you have tried time phasing of source determination using priority (transportation cost rate), please let me know what I am missing.
Thanks,
Krish
Request clarification before answering.
Hi Krish,
Please check out of scope list in SAP Help, so transport cost is supported as static value.

Thanks
Girish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.