Hello,
I'm working in the Supply review phase. we have consensus demand and run TS-Based Supply Heuristic as result Production requirement generates but its components requirement is not created and no capacity utilization happen.
Note :- Each material stock =0.
Could you please help to get the missing point and fix the issue
Thanks in advance
Rajesh Tiwari
Request clarification before answering.
Hello rajtiwari
the 2 iussues that you mentioned maybe or may not be directly related with each other. But below are the points wortjh checking.
1) Is source type P maintained for all source header MDT ?
2) Are the components correctly assigned tot he right source ID ?
3) Have you maintained capacity consmption rate in the production source resource MDT ?
4) Also please run heuristic is check mode and see all the errors and warnings (if any).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 9 | |
| 8 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.