Hello Experts,
Can you please tell me how to transport from the IBP test tenant to the IBP production tenant? Can it be done through Cloud Platform Integration?
What is the process behind moving all my settings in the test tenant to a production tenant? Also, when the Production system is up and running how can we move any new change from test to the production enviroment?
Request clarification before answering.
Hi Argha,
You first need to have a Transportation path set up between your Source (Test) and Target (PROD) systems. Have you already requested that? If not, please raise an incident to SAP Support and it will be redirected it to the Cloud Operations team so the path is defined and you can automatically transport the supported objects between both systems.
The following KBA has the information on these objects as well: https://launchpad.support.sap.com/#/notes/2459286
Please note that the Transport Model Entities functionality only work between systems that are on the same release and same HotFix Collection versions.
Let me know in case of any other questions on this matter.
Best regards,
Ivan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Serhii,
Please refer to the following Help page with the up-to-date info on Transport objects:
Best,
Ivan
Hello Argha,
IBP provides a model transport application. You can choose a planning area and all the related configuration would be transported across to the target system.
Thanks and Regards,
Veera
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 5 | |
| 5 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.