Transfer and update plant specific material master data to S/4 HANA EWM - Cyclic counting indicator

antimparmar1
Discoverer
0 Kudos
495

Hi Experts,

We do ABC analysis in our SAP ERP and then transfer cyclic counting indicator which is in General Plant Data/Stroage1 view of the material master to EWM for S/4 HANA and update it in the warehouse data tab of product master's in real time.

I can take this CC indicator using changes pointer from ERP to EWM as we already use reduced MATMAS for material master replication.

Now, how to update this ABCIN to product master warehouse data tab field CCIND during IDOC processing? Or is there any better way of doing.

Regards,

Antim Parmar

Accepted Solutions (1)

Accepted Solutions (1)

antimparmar1
Discoverer
0 Kudos

Used BTE 1250 and BADI BADI_MATMAS_ALE_IN to update the ABCIN in EWM from ERP.

Use BAPI /SAPAPO/DM_PRODUCTS_MAINTAIN

Regards,

Antim Parmar