Time zones causing unload date on previous day with GATP using Configurable Process Scheduling

Former Member
0 Likes
405

Sales Orders created against a source location in time zone UTC -05:00 and delivered to a customer in time zone UTC -06:00 are showing a Delivery Date a day early when the transit time ends in the first hour of the day. For example, if transit time (TRAN) finishes at 5/15/2017 00:00 and the unload time (UNLD) is zero then the Delivery Date is being calculated as 5/14/2017 23:00 but since CRM only shows the date part it appears to be arriving a day early.

Any guidance offered will be appreciated.

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Answers (0)