We run Time Series Base Supply Planning Heuristic in Infinite without shortages mode. The Capacity usage of Production Resource (PCAPAUSAGE) and the Capacity Demand of Production Resource (PCAPADEMAND) have different values. PCAPADEMAND has the right value but PCAPAUSAGE has a lower value. We have sufficient available capacity.
This results in incorrect Capacity Utilization% impacting the identification of periods where the demand exceeds capacity constraints.
Have any of you seen this issue?
Request clarification before answering.
Hi Krish,
The PCAPADEMAND is calculated as PCAPACONSUMPTION * NETDEMAND, while the PCAPAUSAGE is calculated as PCAPACONSUMPTION * PRODUCTION.
Make sure the heuristic is able to produce all net demand, or is this net demand is being satisfied by another SOS e.g. t-lane.
Best regards,
Matheus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Purge both the KF or respective planning level and check again
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.