When running the Time-Series-Based Supply Planning Heuristic, we always start it in the current technical week. If we would start it in a previous technical week, for example so that the heuristic begins on the 1st of the month, what is the impact?
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
No Impact as it can run from past buckets as well, but you need to have certain inputs on previous week as that you will become your supply planning start week (Example - INITIALINVENTORY Key figure)